Bishop Elementary School
K/1 propane Line replacement - propane line is currently shut off. Trenching project began 9/1/23 to replace / sleeve with new propane line
Methane mitigation - ongoing; site assessment conducted, DTSC environmental oversight agreement in place, severity currently deemed “low”
Fencing - expand Kinder yard to include shaded area behind K/1 building, awaiting materials so Boyd’s can begin the project, add a gate in front of office, gates on walkway next to preschool, TK yard expansion after.
Playground areas prone to flooding - sump pumps purchased & used to clear out surface water on 3rd/4th gd blacktop & TK playground
Construction of Modular Building (2 classrooms, ASP room, & new health office) - modular has been designed and ordered; awaiting DSA approval to begin site work, site work to begin January 2024
Classroom and Hallway Flooring - classrooms and hallways across campus being prioritized by need during 23/24 school year for replacement
Ceiling leaks & stains on ceiling tiles - patching leaks as they arise, roof replacements in long term deferred maintenance plan
Classroom HVAC units - all past expected lifespan
Student Restrooms - outdated, replacements in long term deferred maintenance plan
Fix/replace student water fountains
Home Street Middle School
Library/MP Roof - replacement in long term deferred maintenance plan
Classroom HVAC units - 30 years old, need replacing; 35 units will cost an estimated $300k
Security cameras - installation in progress by ICOE Tech team
Student Restrooms - outdated, replacements in long term deferred maintenance plan
Bishop Union High School
Roof Replacements - ranked by priority
Ag Building - awaiting 9/18/23 mandatory walkthrough; bid packet deadline 10/11/23; estimated job completion date: 12/27/23
Math Building - out to bid (due 12/18/23): multiple classroom leaks; also likely a systemic plumbing/drainage problem
English Building - out to bid (due 12/18/23): multiple classroom leaks; also likely a systemic plumbing/drainage problem
Main Building - multiple classroom leaks
West Gym Locker Room - replacement included in 23/24 budget
HVAC Systems - cooling systems not operating
CLBR
Autoshop
Security Cameras - installation in progress by ICOE Tech team
Student Restrooms - outdated, replacements in long term deferred maintenance plan
Mall/Quad Area - smooth surface and new landscape, clear our sewer line from BSC to street
Alternative Ed Sites
KBS Water Line - replace so doesn’t freeze in winter
Internet Connectivity - Frontier high speed internet service installation
HVAC systems (5) - 30 years old, will need replacing
Replace building ramps
Transportation
• Buses -
ordering 2 new diesel buses, receiving 3 new grant-funded electric buses & charging stations; grant request for charging station infrastructure to be installed by Edison
District
Replace MOT Building - partnership w/ ICOE to replace and also provide space for Tech team
Connectivity - transfer cell phone service provider from Verizon to AT&T/FirstNet